THE NAVARRO REPORT - Los Angeles County has spent nearly two years teaching itself to approve rebuilding permits faster. By most measures, it has succeeded. Yet a permit is a piece of paper, and a family cannot sleep under one. The more urgent question, as the Eaton and Palisades fires recede into the calendar, is why so few homes have actually been finished.
A Tale of Two Numbers
Consider two figures from the past year. In January, CalMatters reported that more than 2,600 residential permits had been issued across the Palisades and Altadena, roughly one for every five of the nearly 13,000 homes lost, with another 3,340 still under review. Then, as of early March, only 13 homes had been completed: one in Pacific Palisades and twelve in the Eaton burn area.
The distance between those numbers is the real story. Permitting was long assumed to be the principal obstacle. It was the visible one, the one that drew hearings, headlines, and political blame. But if permits are now flowing, something else is holding the hammers still.
What the County Fixed
To its credit, the county has made substantial changes. Residents who intend to rebuild what they lost can use a like-for-like process, which skips much of the design review a new home would require. Pre-approved plans give owners a ready-made starting point. An artificial intelligence pilot, known as Archistar eCheck, screens plans for code compliance before a human reviewer ever opens the file. The City of Los Angeles reports that it now reviews complete like-for-like applications within 30 days.
The county has also been willing to examine its own performance. In September, it released a second independent after-action review covering recovery and repopulation from January 7 through March 31, 2025. That report produced 26 substantive findings and 25 actionable recommendations. Those are candid numbers for a government to publish about itself, and they deserve follow-through.
The Bottlenecks Beyond the Permit Counter
So where does the process stall? Several plausible culprits emerge, and each deserves reporting rather than speculation.
Financing and insurance. Homeowners must often carry a mortgage on a destroyed house while paying rent elsewhere, and insurance payouts have frequently fallen short of today's construction costs. Many owners cannot start building until a settlement is resolved. Others cannot afford to.
Cost and the new building standard. California's updated Wildland-Urban Interface Code took effect on January 1, 2026. Homes going up must meet a stricter fire-resistance standard, which is sensible for safety but adds expense. Meanwhile, the properties involved were hardly modest. One analysis put the median pre-fire sale price at about $1.04 million in Altadena and $2.93 million in Pacific Palisades. Rebuilding at that scale demands capital that many working families simply lack.
Contractors, labor, and utilities. A sudden surge in demand strains every trade at once. In October 2025 alone, permit activity across both zones peaked at 1,954 filings, more than five times the pre-fire baseline. Crews cannot be conjured on schedule, and a lot still waiting for reconnected power, water, or gas cannot host a finished house, whatever its paperwork says.
The sell-or-rebuild decision. Some residents have quietly concluded that selling the land is more realistic than rebuilding. If a meaningful share of lots change hands to developers, the neighborhoods that emerge may look very different from the ones that burned.
What the Dashboard Can and Cannot Tell Us
The county's Permitting Progress Dashboard is a useful instrument. It tracks applications, review times, and permits issued for both fire areas, and it is updated regularly. Transparency of this kind is a genuine improvement over the opening weeks, when the tracker showed four permits for the Eaton Fire and none for the Palisades.
But a dashboard that measures permits will naturally tell a story about permits. It is far less revealing about what happens after approval. The consequent gap in public knowledge is significant. Residents, and the supervisors who answer to them, need a comparable measure of progress that runs from permit to groundbreaking to certificate of occupancy. What gets measured gets managed, and right now the finish line is barely measured at all.
Questions for the Board of Supervisors
The after-action review offers a roadmap, and the county has said residents can follow the status of adopted recommendations online. That promise is only meaningful if someone is reading. Supervisors should be asked a few plain questions.
How many of the 25 recommendations have been adopted, and how many are actually implemented? What is the average time between permit issuance and construction start? How many permitted lots have changed ownership? And what is the county doing to help owners who hold a permit but cannot finance the build?
The answers will not all be flattering. They will, however, be explicit, and they will tell residents whether the next phase of recovery requires better paperwork or better money.
The Measure That Matters
Wildfire season has returned to Southern California. Earlier this month, county agencies urged residents to prepare for a Red Flag Warning and strong Santa Ana winds, a reminder that the region's exposure has not diminished while the rebuilding drags on. Every vacant lot in a burn scar is a reminder of what was lost and, increasingly, a question about who will return.
The county deserves credit for clearing the permit counter. Now it must be held to a harder standard. A permit is a promise to build. The measure of recovery is the porch, the kitchen light, the family at the table. Until those numbers rise, speed at the permit window is only half a success.
(Jose E. Navarro, MBA, is a San Diego–based financial controller, public finance analyst and founder of The Navarro Report. With more than 20 years of experience in public finance, nonprofit management and government contract compliance, he writes about government spending, transparency and public accountability.)